| PLANNED MAINTENANCE 15 – 21 NOVEMBER 2021 | | | |
| DATE | AREA AND LOCATION/STREET | START | COMPLETION FORECAST |
| 15 November | Constantia: Zonnestraal, Alphen and Upper Alphen substations, Peter Cloete, Vineyard, Alphen and Leith. | 09:00 | 16:00 |
| 16 November | Century City: Emerald Way, Ploughmans Crescent, Summer Greens and vicinity. | 08:00 | 16:00 |
| 16 November | Rocklands: Bronze, Silver, Sapphire and vicinity. | 08:00 | 16:00 |
| 16 November | Diep River: Annandale substation, Fairmead, Fairdale, Edgewear, Old Kendal, Pineview, Melrose Place, Suring and Mimosa. | 09:00 | 16:00 |
| 17 November | Somerset West: Lourens, Reitz, Fagan, Andries Pretorius and Hunterslane | 08:00 | 18:00 |
| 17 November | Constantia: Porter, Parade and Firgrove. | 09:00 | 16:00 |
| 17 November | Constantia: Klaasenbosch substation, PM 372 substation, Sun Valley, Versveld, Tanja, Brommersvlei, Eugene and Marais. | 09:00 | 16:00 |
| 18 November | Claremont: Scott, Crescent, Molteno, Ripelby, Main and Firs. | 06:00 | 18:00 |
| 18 November | Rondebosch: Muir Road substation, Garton, Portland, Weltevreden and Swanmore. | 06:00 | 16:00 |
| 19 November | Newlands: Chinese Embassy substation, Kirstenwood substation, Orchard Heights, Rhodes, Alow, Willow, Briar and Almond . | 09:00 | 16:00 |
| 19 November | Newlands: Fernwood substation, Shamrock substation, Poplar, Birch, Thorn, Bisset, Prospect and Upper Holly. | 09:00 | 16:00 |
| 20 November | Kraaifontein: Hofmeyer, Milton | 08:30 | 18:00 |
| 20 November | Kraaifontein: Drostdy and Peerless Park North, | 08:30 | 18:00 |
| 21 November | Maitland: Loco Road. | 05:30 | 16:00 |
| 21 November | Llandudno: Llandudno substation, Gully, Maori, Liermans and Logiesbay | 06:00 | 14:00 |