Skip to content

Search

Menu

Areas affected by required electricity maintenance for 15 – 21 November 2021

12 November 2021

The City of Cape Town thanks customers for their patience as we do necessary maintenance on our electrical infrastructure next week in various areas of the metro. This will necessitate supply interruptions for the safety of all concerned. Read more below:

The areas that will be affected by electricity supply interruptions due to necessary maintenance are:

PLANNED MAINTENANCE 15 – 21 NOVEMBER 2021
DATEAREA AND LOCATION/STREETSTARTCOMPLETION FORECAST
15 NovemberConstantia: Zonnestraal, Alphen and Upper Alphen substations, Peter Cloete, Vineyard, Alphen and Leith.09:0016:00
16 NovemberCentury City: Emerald Way, Ploughmans Crescent, Summer Greens and vicinity.08:0016:00
16 NovemberRocklands: Bronze, Silver, Sapphire and vicinity.08:0016:00
16 NovemberDiep River: Annandale substation, Fairmead, Fairdale, Edgewear, Old Kendal, Pineview, Melrose Place, Suring and Mimosa.09:0016:00
17 NovemberSomerset West: Lourens, Reitz, Fagan, Andries Pretorius and Hunterslane08:0018:00
17 NovemberConstantia: Porter, Parade and Firgrove.09:0016:00
17 NovemberConstantia: Klaasenbosch substation, PM 372 substation, Sun Valley, Versveld, Tanja, Brommersvlei, Eugene and Marais.09:0016:00
18 November

Claremont: Scott, Crescent, Molteno, Ripelby, Main and Firs.

 

06:0018:00
18 NovemberRondebosch: Muir Road substation, Garton, Portland, Weltevreden and Swanmore. 06:0016:00
19 NovemberNewlands: Chinese Embassy substation, Kirstenwood substation, Orchard Heights, Rhodes, Alow, Willow, Briar and Almond .09:0016:00
19 NovemberNewlands: Fernwood substation, Shamrock substation, Poplar, Birch, Thorn, Bisset, Prospect and Upper Holly.09:0016:00
20 NovemberKraaifontein: Hofmeyer, Milton 08:3018:00
20 NovemberKraaifontein: Drostdy and Peerless Park North,08:3018:00
21 NovemberMaitland: Loco Road.05:3016:00
21 NovemberLlandudno: Llandudno substation, Gully, Maori, Liermans and Logiesbay 06:0014:00

*Information is complete and correct at time of publication, but subject to change due to weather and other unforeseen conditions.

*It is the standard practice to notify customers of planned maintenance via a pamphlet delivered door-to-door ahead of work.

Tips:

  • Where possible, please switch off appliances at the wall socket ahead of maintenance to reduce the risk of damage caused by power surges.
  • The supply could be restored at any time therefore residents should remember to treat all electrical installations as live for the full duration of the interruption.

Please note: Eskom's load-shedding typically cause power faults due to nuisance tripping and increased service requests.

Please wait at least 30 minutes before logging a service request alerting the City that the power in your area has not come back after load-shedding. Sometimes, the issue is already being resolved. City teams will do their best to attend to any outages as soon as possible.

City's service channels (don't log the same request multiple times on multiple channels as this contributes to delays):

Call Centre: 0860 103 089

SMS: 31220 (standard charges apply)

Online: www.capetown.gov.za/servicerequests

 

Published by:
City of Cape Town, Media Office

You have disabled JavaScript on your browser.
Please enable it in order to use City online applications.